Cleveleys Sea Wall Reconstruction

Cleveleys, UK

Cleveleys Sea Wall Reconstruction

Project outline

The concrete sea wall at Cleveleys had been constructed in various stages.  The existing concrete apron and sheet pile cut-off at beach level had suffered severe abrasion damage from shingle and sand.

We undertook a detailed structural investigation of the existing structure, this determined that refacing the apron, grouting and providing concrete protection to the upper section of sheet pile would re-establish a satisfactory standard of coastal defence.

We also undertook a benefit cost assessment and prepared an Engineering Report for submission to MAFF.  A design was completed, which featured the use of fibre and steel reinforced concrete.  The works were undertaken over a twelve-week period.

All work was carried out on a tidal basis using a purpose built face shutter, designed by the contractor in accordance with specified requirements.

Contract value

£12m

   
 